The Gantt chart is a visual view of scheduled tasks over time. Gantt charts are used to plan projects of all sizes and are a useful way to show the work scheduled for a specific day. They also help you display the start and end dates of a project in a simple view.

This tool meets two objectives: plan optimally as well as communicate on the established schedule and the choices it imposes.

The diagram allows:

  • to determine the dates of completion of a project.
  • to identify the existing margins on certain tasks.
  • to visualize at a glance the delay or the progress of the work.

The Gantt chart does not solve all the problems, especially if you have to plan productions that compete for the use of certain company resources.

Method

The method consists in placing the tasks to be carried out in the in the order defined by the priority and taking into account the resources still available. The most common rules are:

  • priority to the completion of products with the earliest delivery date.
  • priority to the first order arrived.
  • priority to productions with the shortest total duration.
  • priority to fabrications that use at least one critical resource.
  • priority to products that have the minimum margin.

This diagram (or schedule) has a number of advantages:

  • easy to read and accessible to all.
  • monitoring can be done easily during the course of the project by comparing
    the planned dates and the actual dates.
  • the start and end dates of each task are read directly from the scale of
    time.
  • it allows by assigning resources to tasks to establish the load plan.
The diagram is represented on two axes: time and allocation (often a task can only be assigned to a dedicated entity); and contains two types of elements: bars representing a task and its execution time, and arrows representing the anteriority links.

The Gantt chart makes it possible to analyze all the relationships that exist between the activities, to identify the sequences of activities, to identify the critical path (without leeway) and the start and end dates (at the earliest and at the latest) of each activity. The Gantt chart makes it possible to choose the dates which will be effectively retained to carry out the activities and, possibly, to show the relations between the activities and therefore the incidences in terms of delay.

Drawing a Gantt chart should be done in three steps:

  1. Determine and structure the list of tasks by declaring the antecedents or other constraints.
  2. Create the task diagram (time criterion). For each of them, it is necessary to determine the duration as well as the leeway.
  3. Complete the diagram with the other criteria.

Example

Gantt chart allocation tasks execution time

Establishment of the temporal diagram:

Addition of criteria (here the number of staff to accomplish a task: